  1. BuB 2015 – Other Local Infrastructure Project
  2. FY 2015 Budget
  3. LOCAL GOVERNMENT OF SIBUTAD
  4. Name of Implementing Partner
  5. Subproject Implementation Schedule
  6. Project Title: Construction of Evacuation Center
  7. Location : Barangay Magsaysay, Sibutad, Zamboanga del Norte
  8. Sn Activity Timelines
  9. Duration Start Finish
  10. 1.00 DED PREPARATION
  11. 1.01 Preparation of DED 15 June 13, 2016 July 1, 2016
  12. 1.02 Submission to DILG 1 July 5,2016 July 5, 2016
  13. 2.00 SUBPROJECT REVIEW/APPROVAL
  14. 2.01 Endorsement to PTWG/ PDMU 1 July 7, 2016 July 7, 2016
  15. 2.02 Review by PTWG/ PDMU 2 July 11, 2016 July 12, 2016
  16. 2.03 Approval by DILG Provincial/ Regional Director 1 July 14, 2016 July 14, 2016
  17. 2.04 Confirmation letter to LGU on the Approval of the DED 2 July 15, 2016 July 15, 2016
  18. 3.00 PROCUREMENT PROCESS
  19. 3.01 Bid Preparation 3 August 8, 2016 August 10, 2016
  20. 3.02 Pre-Procurement Conference 1 August 11, 2016 August 11, 2016
  21. 3.03 Ad/ Posting ITB 7 August 12, 2016 August 18, 2016
  22. 3.04 Pre-bid Conference 1 August 22, 2016 August 22, 2016
  23. 3.05 Submission and Receipts of Bids 10 August 23, 2016 September 1, 2016
  24. 3.06 Opening of Bids 2 September 5, 2016 September 6, 2016
  25. 3.07 Bid Evaluation 3 September 7, 2016 September 9, 2016
  26. 3.08 Post Qualification 5 September 12, 2016 September 16, 2016
  27. 3.09 Issuance of BAC Resolution w/ BER 1 September 19, 2016 September 19, 2016
  28. 3.10 Issuance of Notice of Award 4 September 20, 2016 September 23, 2016
  29. 3.11 Contract Signing 1 September 26, 2016 September 26, 2016
  30. 3.12 Issuance of Notice to Proceed 2 September 28, 2016 September 29, 2016
  31. 4.00 CONSTRUCTION/ IMPLEMENTATION
  32. 4.01 Mobilization 7 September 30, 2016 October 7, 2016
  33. 4.02 Implementation 150 October 10, 2016 April 3, 2017
  34. 4.03 Punch Listing 2 April 6, 2017 April 7, 2017
  35. 4.04 Acceptance 1 April 11, 2017 April 11, 2017
  36. Prepared by: Approved by:
  37. ENGR. JONATHAN REDILLAS HON. EUFRACIO D. CAIDIC
  38. Municipal Engineer Municipal Mayor
  39. Concurred by:
  40. LERMA M. CAMPANER
  41. DILG Provincial Director