  1. CALGARY -- Nexen Energy says it is laying off about 350 employees after shelving plans to restart a facility at an Alberta oilsands operation that was damaged in a fatal explosion earlier this year.
  2. The company idled an upgrader at the Long Lake site after an explosion in January killed two people.
  3. After a review, Nexen has concluded that a short-term repair for the upgrader is not feasible and therefore it is putting it into winter preservation mode with no date set for a restart.
  4. Nexen says the explosion was the result of work being performed outside the scope of approved work activities.
  5. The company has also finished an investigation into a pipeline leak last year that spilled about five million litres of bitumen, sand and produced water over a 16,000-square metre area.
  6. The company concluded that the rupture happened on June 11 -- about a month before it was discovered by a contractor -- was a result of an incompatible pipeline design for the muskeg ground conditions.